Krishna Godavari Onshore Block

KG-ONN-2004/1

Krishna Godavari Onshore Block 

September 14, 2006 Agreement with OIL to increase our PI up to 25%
March 2, 2007 Signed Production Sharing Contract (NELP VI) 
March 24, 2007 Applied for Production Exploration License
September 14, 2007 Amended application for Production Exploration License into two parts
February 18, 2008 Partial Production Exploration License issued (on 511 sq. km. only)
Area Approximately 549 sq. km. (135,660 acres)
GGR PI  10%
Partners Oil India Limited = 90% (operator)

 

Block Commitments
Total wells to be drilled in all Phases is 13 (12+1)

Phase I (4.0 years) February 18, 2008 to February 17, 2012
(i) Reprocessing 564 line km. of 2D seismic
(ii) Gravity magnetic and geochemical survey
(iii) Seismic acquisition program consisting of 548 sq. km. of 3D seismic
(iv) Drill 12 exploration wells to various depths between 2,000 and 5,000 meters
Phase II (3.0 years) February 18, 2012 to February 17, 2015
(v) Drill 1 exploration well to 4,600 meters
Land Relinquishment
(i) Phase I – not less than 25%
(ii) Phase II – 100% except for development and discovery areas